Hampden Park North Stand Concourse Extension

Residents Information Newsletter/ December 2012

     

Newsletter 2


Dear Resident,


Please find enclosed within this newsletter a brief update with
regards to progress and forthcoming works on the Hampden Park

North Stand Concourse Extension


If you have any queries with regards to the ongoing construction
works please feel free to contact Vanessa Todd on 07875 201067 or
alternatively email Vanessa.todd@isgplc.com


Site Progress


Piling works are now complete on Somerville Drive.


Ground beam foundations are almost complete.


Steel frame structure will commence early January, during this time
a crane will be required to occupy a section of the road, in order for
this to mitigate as much disruption as possible we will extend our site
fence line further into the road to accommodate these works. We will
ensure adequate access to all properties on Somerville Drive at all
times.


Making good of the ground outside the north stand will commence
early January.


Concrete cladding panels to ground floor level will commence mid
January.


Site Christmas Holidays & January Site Hours


During the Christmas period the ISG site will close Friday 21st
December and re-open Thursday 3rd January 2013. On return from
the festive break extended working hours and weekend work will be
in place throughout January


Contract Duration


This contract is due for completion May 2013



For further information or to discuss the construction works please call Vanessa Todd/Customer Care Manager 07875201067